Subject:
|
Measure R: Change Orders 6A, 4C, 7D, and 4E - Modular Classroom Projects
|
District Priorities:
|
|
Enclosure
|
|
File Attachment:
|
|
Summary:
|
In accordance with the District's change order approval process, the following change orders are in connection with the replacement the oldest portables located at Fammatre, Farnham, Sartorette, and Price Middle School.
The total change orders for larger modernization projects typically range from 6% - 8%. The attached change orders total a credit of $256,674.23 which represents a -3.68% change of the total contracts listed of $6,976,282.00.
6A: Galeb Paving CO credit of $160,306.16
4C: McGuire & Hester CO $856.00
7D: Cupertino Electric CO credit of $2,500
4E: Scapes CO credit of $94,724.07
|
Funding:
|
|
Recommendation:
|
Staff recommends that the Governing Board ratify the four (4) necessary change orders; 6A, 4C, 7D, and 4E, in connection with the Modular Classroom Projects.
|
Approvals:
|
Recommended By:
|
Signed By:
|
|
Carlena Grandey - Administrative Assistant to the Superintendent
|
|
Signed By:
|
|
Kristi Schwiebert - Superintendent
|
|
|
|
|
|
|
|