Subject: Measure R: Change Orders 11E and 12A - Phase 1 Modernization Projects
District Priorities:
Enclosure
File Attachment:
CSD Ph1 Mods - BMI CO #12A 06.01.23.pdf
CSD Ph1 Mods - BMI CO #11E 06.01.23 rev.pdf
Summary: In accordance with the District's change order approval process, the following change orders are in connection with the Phase 1 Modernization Project to replace the aging HVAC systems at Bagby, Fammatre, Farnham, Sartorette, and Price Middle School.

The total change orders for larger modernization projects typically range from 6% - 8%. The attached change orders total $42,255 credit which represents a 1.05% change of the total contracts listed of $4,321,110.00.

11E: Beals Martin and Associates, Inc. (Farnham & Sartorette) $13,290.00 - Credit
12A: Beals Martin and Associates, Inc. (Bagby, Fammatre, & Price) $31,965.00 - Credit
Funding:
Recommendation: Staff recommends that the Governing Board ratify the two (2) necessary change orders, 11E and 12A in connection with the Phase 1 Modernization Projects.
Approvals:
Recommended By:
Signed By:
Carlena Grandey - Administrative Assistant to the Superintendent
Signed By:
Kristi Schwiebert - Superintendent