Subject: Measure R: Change Orders 8C, 10E, and 11A - Phase 1 Modernization Projects
District Priorities:
Enclosure
File Attachment:
CSD Ph1 Mods - MBS Eng. CO #8C 04.06.23.pdf
CSD Ph1 Mods - BMI CO #10E 04.06.23.pdf
CSD Ph1 Mods - BMI CO #11A 04.06.23.pdf
Summary: In accordance with the District's change order approval process, the following change orders are in connection with the Phase 1 Modernization Project to replace the aging HVAC systems at Bagby, Fammatre, Farnham, Sartorette, and Price Middle School.

The total change orders for larger modernization projects typically range from 6% - 8%. The attached change orders total $81,188.37 which represents a 1.62% change of the total contracts listed of $5,013,322.00.

8C: MBS Engineering (Bagby, Fammatre, & Price) $15,807.37
10E: Beals Martin and Associates, Inc. (Farnham & Sartorette) $2,242.00 - Credit
11A: Beals Martin and Associates, Inc. (Bagby, Fammatre, & Price) $67,623.00
Funding:
Recommendation: Staff recommends that the Governing Board ratify the three (3) necessary change orders, 8C, 10E, and 11A, in connection with the Phase 1 Modernization Projects.