Meeting Date: 3/16/2023 - 7:00 PM
Category: Information and Study Items
Type: Action
Subject: Measure R: Change Orders 5D and 6B - Phase 1 Modernization Projects
District Priorities:
Enclosure
File Attachment:
CSD Ph1 Mods - Pfeiffer CO #6B 03.16.23.pdf
CSD Ph1 Mods - Smith MEP CO #5D 03.16.23.pdf
Summary: In accordance with the District's change order approval process, the following change orders are in connection with the Phase 1 Modernization Project to replace the aging HVAC systems at Bagby, Fammatre, Farnham, Sartorette, and Price Middle School.

The total change orders for larger modernization projects typically range from 6% - 8%. The attached change orders total $56,793.76 which represents a 1.18% change of the total contracts listed of $4,803,461.00.

5D: Smith Mechanical-Electrical-Plumbing CO (Bagby, Fammatre, & Price) $61,140.90
6B: Pfeiffer Electric CO (Bagby, Fammatre, & Price) $4,347.14 - Credit
Funding:
Recommendation: Staff recommends that the Governing Board ratify the two (2) necessary change orders, 5D and 6B, in connection with the Phase 1 Modernization Projects.