|
|
|
|
|
|
Meeting Date:
|
12/19/2024 - 7:00 PM
|
Category:
|
Information and Study Items
|
Type:
|
Action
|
Subject:
|
Measure R: Resolution 24-25-05 - Declaring The Futility of Public Bidding for Site Concrete Trade Services for Increment 1 Sitework for Modular Classrooms at Fammatre, Farnham, Sartorette, and Price Middle Schools
|
District Priorities:
|
|
Enclosure
|
|
File Attachment:
|
|
Summary:
|
On May 18, 2023, the Board awarded McGuire and Hester (formerly named Casey-Fogli Concrete at the time of bid) for the Site Concrete Trades, for the Increment 1 Sitework for Modular Classrooms at Fammatre, Farnham, Sartorette, and Price Middle School based on their low bid. Due to required accessibility (ADA) upgrades for state certification, a 14.51% increase over the original contracted amount was required. A resolution is required to continue with McGuire and Hester. It has been concluded that their costs are reasonable and going out to rebid the project would delay the project and result in unnecessary expenses to the District.
|
Funding:
|
|
Recommendation:
|
Staff recommends that the Governing Board approve Resolution 24-25-05 and allow Cambrian to continue working with McGuire and Hester and complete Increment 1 Sitework for Modular Classrooms at Fammatre, Farnham, Sartorette, and Price Middle School.
|
Approvals:
|
Recommended By:
|
Signed By:
|
|
Carlena Grandey - Administrative Assistant to the Superintendent
|
|
Signed By:
|
|
Kristi Schwiebert - Superintendent
|
|
|
|
|
|
|
|