|
Meeting Date:
|
|
Category:
|
Information and Study Items |
|
|
Type:
|
|
Subject:
|
Measure R: Change Orders 1A, 1B, and 1D - HVAC in the Common Areas at Bagby, Farnham, and Sartorette |
|
|
District Priorities:
|
|
Enclosure:
|
|
File Attachment:
|
|
Summary:
|
In accordance with the District's change order approval process, the following change orders are in connection with the replacement of the HVAC equipment in common areas (e.g., offices, libraries, multi-use buildings, etc.) located at Bagby, Farnham, and Sartorette.
The total change orders for larger modernization projects typically range from 6% - 8%. The attached change orders total $103,513.20 which represents a 4.54% change of the total contracts listed of $2,281,018.00
1A: Beals Martin and Associates, Inc. $
1B: Best Electrical CO $
1D: O.C. McDonald CO $ |
|
|
Funding:
|
|
Recommendation
|
Staff recommends that the Governing Board ratify the three (3) necessary change orders; 1A, 1B, and 1D, in connection with the HVAC projects in the Common Area at Bagby, Farnham, and Sartorette. |
|
|
Approvals:
|
Recommended By: |
Signed By: |
|
Carlena Grandey - Administrative Assistant to the Superintendent |
|
Signed By: |
|
Kristi Schwiebert - Superintendent |
|
|
|
|
|
|
|